[{"data":1,"prerenderedAt":61},["ShallowReactive",2],{"q-105170-arch_law-65":3},{"question":4,"neighbors":26,"sameNumber":45,"prev":34,"next":37},{"id":5,"classKey":6,"session":7,"year":8,"subject":9,"number":10,"groupStem":11,"ownStem":12,"stem":12,"options":13,"answer":18,"answerKind":20,"answerS":11,"answerNote":11,"images":21,"explanation":22,"withheld":11,"deepChars":23,"freq":24,"indexable":25},"arch-105170-801-0101-065","architect","105170",105,"營建法規與實務",65,null,"依行政院公共工程委員會制定之「公共工程技術服務契約範本」，下列何者不符合履約期限延期條件？",{"A":14,"B":15,"C":16,"D":17},"甲方要求全部或部分暫停履約","非可歸責於乙方之情形，經甲方認定者","因辦理契約變更或增加履約標的數量或項目","乙方應辦事項未及時辦妥",[19],"D","single",[],"本題考點：公共工程技術服務契約範本中「履約期限延期」的要件——延誤須因不可歸責於廠商（乙方）之事由，並經機關（甲方）審查認定，才可展延履約期限。\n【正解理由】履約期限是契約雙方約定的給付時點，廠商逾期原則上要負逾期責任。延期條款是這個原則的例外，其核心判準只有一個：延誤的原因是否「不可歸責於乙方」。契約範本所列的延期事由，例如甲方要求全部或部分暫停履約、甲方辦理契約變更或增加履約標的數量或項目、其他非可歸責於乙方而經甲方認定的情形，共同點都是延誤原因落在甲方或外部，乙方無從控制。反過來說，延誤若源自乙方自己的作為或不作為，就應由乙方承擔，不得藉延期轉嫁風險。選項 (D)「乙方應辦事項未及時辦妥」正是可歸責於乙方的典型情形，不符合延期條件，故選 D。\n【逐項排除】\n(A) 符合延期條件。暫停履約是甲方發動的指示，乙方依指示停工，停工期間無法推進工作，延誤原因在甲方，故可展延。\n(B) 符合延期條件。這是延期事由的概括條款：只要延誤非可歸責於乙方，並經甲方審查認定，即得展延。「經甲方認定」這道程序，是為了避免乙方自行宣稱不可歸責而任意延期。\n(C) 符合延期條件。契約變更或增加履約標的數量、項目，代表工作量由甲方決定擴大，原定期限是依原工作量估算，自然應隨之調整。\n(D) 不符合延期條件。乙方應辦事項本屬乙方的契約義務，未及時辦妥是乙方自身的履約遲延，屬於可歸責於乙方的事由，不能據以展延；若反過來是「甲方應辦事項未及時辦妥」致乙方無法履約，才屬可延期的情形。\n【記憶點】延期看歸責：原因在甲方（暫停、變更、增量）或外部而經甲方認定者可延；原因在乙方自己者不可延。",513,1,true,[27,30,33,36,39,42],{"number":28,"session":7,"stem":29},62,"下列何者為機關委託技術服務廠商評選及計費辦法中屬於專案管理之工作？①設計進度之管理及…",{"number":31,"session":7,"stem":32},63,"依據政府採購法第六章爭議處理有關申訴審議委員會組成之敘述，下列何者錯誤？",{"number":34,"session":7,"stem":35},64,"依據機關委託技術服務廠商評選及計費辦法，下列何者應另予增加費用？①於設計核准後須變更…",{"number":37,"session":7,"stem":38},66,"依政府採購法採購評選委員會組織準則，下列何者不是評選委員名單產生方式？",{"number":40,"session":7,"stem":41},67,"依據最有利標評選辦法，下列何者不應屬於最有利標之評選項目及子項？",{"number":43,"session":7,"stem":44},68,"依政府採購法及其相關子法規定，機關委託廠商辦理技術服務，其服務費用採建造費用百分比法…",[46,49,52,55,58],{"number":10,"session":47,"stem":48},"114180","下列何種採購須依政府採購法之規定辦理？",{"number":10,"session":50,"stem":51},"113190","依採購評選委員會組織準則規定，評選委員會召集人由誰擔任？",{"number":10,"session":53,"stem":54},"112190","依公寓大廈管理條例規定，下列何者非屬新建建築物起造人應盡之職務或義務？",{"number":10,"session":56,"stem":57},"111180","依營造業承攬工程造價限額工程規模範圍申報淨值及一定期間承攬總額認定辦法規定，營造業承…",{"number":10,"session":59,"stem":60},"110180","依機關委託技術服務廠商評選及計費辦法規定，機關辦理新建建築物規劃、設計之技術服務採購…",1791863213401]