[{"data":1,"prerenderedAt":61},["ShallowReactive",2],{"q-114180-arch_construction-76":3},{"question":4,"neighbors":26,"sameNumber":45,"prev":34,"next":37},{"id":5,"classKey":6,"session":7,"year":8,"subject":9,"number":10,"groupStem":11,"ownStem":12,"stem":12,"options":13,"answer":18,"answerKind":20,"answerS":11,"answerNote":11,"images":21,"explanation":22,"withheld":11,"deepChars":23,"freq":24,"indexable":25},"arch-114180-801-0103-076","architect","114180",114,"建築構造與施工",76,null,"關於公共工程經費估算中的工程預備費和物價調整費，下列何者正確？",{"A":14,"B":15,"C":16,"D":17},"工程預備費基於間接成本估算，用於因應資料不完整","物價調整費根據固定比例估算，用以對抗未來物價波動","工程預備費應忽略工程規模或特性，統一採用固定百分比估算","物價調整費基於直接成本、間接成本與預備費總和，考慮基準年物價進行調整",[19],"D","single",[],"本題考點：公共工程經費估算中「工程預備費」與「物價調整費」的用途、估算基礎與考量因素之區分。\n【正解理由】物價調整費用來反映「估算時採用的基準年價格」到「實際施工年度價格」之間的物價變動。它的計算基礎是以基準年價格估出的成本總和——直接工程成本、間接工程成本，再加上工程預備費——並依基準年物價與各年度工程款的分配逐年調整。工程預備費之所以也要納入，是因為預備費同樣以基準年價格估列，將來動用時一樣會受物價變動影響。選項 (D) 的計算基礎與調整概念都正確。故選 D。\n【逐項排除】\n(A) 錯誤。用途寫對、基礎寫錯：工程預備費確實是用來因應規劃設計階段資料不完整、數量與項目不確定可能增加的費用；但它的估算基礎是工程本身的成本，而不是間接成本。改成「工程預備費以工程成本為基礎估算，用於因應資料不完整」才對。\n(B) 錯誤。物價調整費不是套一個固定比例：它要依物價變動趨勢、基準年與施工期程中各年度的工程款分配逐年計算，施工期越長、後期工程款占比越高，調整費就越高。改成「物價調整費依物價變動趨勢與分年工程款估算」才對。\n(C) 錯誤。工程預備費的比例不能忽略工程規模或特性：資料越不完整、工程越複雜、不確定性越高，比例應越高；設計越接近完成、數量越確定，比例就越低。改成「工程預備費應考量工程規模、特性與資料完整程度訂定比例」才對。\n(D) 正確。物價調整費以直接成本、間接成本與預備費的總和為基礎，再以基準年物價為起點，考慮施工期間物價變動加以調整，敘述完整無誤。\n【記憶點】預備費管「不確定」、物價調整費管「時間」；物價調整費的基礎是直接成本＋間接成本＋預備費的總和。",545,1,true,[27,30,33,36,39,42],{"number":28,"session":7,"stem":29},73,"建築物之地下層開挖所造成之塌陷如圖所示，當該地屬於透水性良好的土壤，由於開挖時基地內…",{"number":31,"session":7,"stem":32},74,"有關建築資訊模型（BIM），下列敘述何者錯誤？",{"number":34,"session":7,"stem":35},75,"分工結構圖係指依作業性質之不同，將工程細分至一易於掌握、管理的單位，以作為時程管理、…",{"number":37,"session":7,"stem":38},77,"有關鋼結構製造之品質管制內容，不包括下列何者？",{"number":40,"session":7,"stem":41},78,"根據公共工程施工品質管理作業要點，下列那一項對監造單位的工作重點敘述錯誤？",{"number":43,"session":7,"stem":44},79,"施工架為便於工程施工而建造之臨時性設施，下列為其估價要點，何者錯誤？",[46,49,52,55,58],{"number":10,"session":47,"stem":48},"113190","若有一棟位於海邊（高鹽害環境、高度日曬）的私人豪宅別墅，其外牆及屋頂指定採用金屬板材…",{"number":10,"session":50,"stem":51},"112190","關於磁磚張貼完成後的檢查作業，下列敘述何者錯誤？",{"number":10,"session":53,"stem":54},"111180","有關價值工程之敘述，下列何者錯誤？",{"number":10,"session":56,"stem":57},"110180","下列何者為價值工程（VE）最佳使用效益？",{"number":10,"session":59,"stem":60},"109180","鋼構建築中，因跨距太大，大梁與小梁接合處會讓梁產生左右彎曲或扭曲等現象，用什麼方法解…",1791863196584]